Lake Side, Hagley Park.
Hagley Park played host to multiple stages for Lakes Festival 2025, with TES taking charge of two of them, A Stage and B Stage, each needing a build that could carry a full day of sets in front of a big outdoor crowd, the kind of build where the lighting, screen and rig all need to hold up from the first act to the last.
On A Stage, TES handled the lighting, video, rigging and effects. A grandMA3 full-size console drove the lighting rig, MegaPointe moving heads, B-Eye wash fixtures, tilt strobes and ShowPro LED blinders, while Riedel Bolero kept the TES crew talking to each other across FOH and stage throughout the day.
Behind the performers sat an 8 x 4 metre Absen PL V2 LED wall, IP rated for the outdoor setting, with additional panels and ACME pixel line fixtures either side to carry the screen further out. Ten tonnes of chain motors and Global Truss held the rig up, Prolyte barrier kept the crowd in check at the front, and hazers, smoke and CO2 jets gave the lighting somewhere to land. Two Lightspace lasers closed out the visual package for the headline sets.
On B Stage, TES took on both the staging and the lighting. ACME Pixel Line IP fixtures and Chauvet Rogue Outcast BeamWash units ran off a grandMA3 onPC command wing, with a pair of Martin Magnum fog machines and hazers keeping the atmosphere thick through the day.
The stage itself was built from the ground up: F34 truss towers on steel ground support carried the structure, braced with water ballast and steel bracing to hold steady outdoors, with a shadesail rigged as backup for wet weather. A full deck of stage platforms, a raised DJ platform and viewing deck, ramps and handrail gave performers and crew safe footing throughout the day, with Prolyte barrier keeping the crowd at a safe distance out front.
A full deck of stage platforms, a raised DJ platform and viewing deck, ramps and handrail gave performers and crew safe footing throughout the day
Running lighting, video and rigging as one build kept those systems talking to a single console and cue, so A Stage came together cleanly from setup through to the final set. Over two days of setup and show, A Stage held a big, energetic crowd through sets from Maribou State, Alix Perez and Sam Gellaitry, before Wilkinson and Kettama closed the night back to back without a hitch, while B Stage carried its own crowd through the day’s sets.
The reviews backed it up. Rolling Stone Australia said the atmosphere “had me in a chokehold,” with the crowd staying on well past the final set, while RNZ’s writeup singled out the production itself, noting the “visual pyrotechnics locked into gear on the main stage for the final hours” as Kettama and Wilkinson closed the night.
It’s this kind of high end lighting and visual effects work TES does best. Wherever you are in New Zealand, the team can plan, design and deliver a build like this under one roof. Get in touch with TES to talk through your next stage.